Inspection Update

Well yesterday we had our Temp Power Inspection and we PASSED!!!! Yah!!! I also called the electric company which said it would 3-4 days from today before we would see power.  So today Rob and I after going to his Orthopaedic appt went and picked up some stuff for the a/c to finish it up.  He found out when he started cutting into the line that he had a live wire (zap).  They jumped our 6 foot fence (locked) and installed the meter and turned the power on.... CRAZY!!!  Also yesterday with the help of a new friend we finished the drywall.  We also had help from my girlfriend Teresa and her son over the weekend and also a couple we have friended here.  We are very blessed with all the help we have received.  Tommorrow or thursday I will run by and take some photos.  I need to finish screwing in all the drywall, start mudding and finish laying the floor in the temporary kitchen.  YAH!!! Getting closer.  We have also lengthened our lease by 2 weeks so we can get in with out stressing out.  So, whats left to do:

Kitchen:
*Install cabinets, sink, remainder of floor and applainces (including bleaching my very nasty fridge)
Bathroom:
*Install enclosure around tub and finish plumbing
Master Bedroom:
* Patch Ceiling
** Finishing Screwing in Drywall, then mud and paint.
Outside:
* Install skirting, finish grading, add small deck w/ steps at each door
A/C
* Clean Ducts, Install Filter Ducts, Install the heater strips, hook up the power and run them
* Cover Ducting on side of the house.
Water:
** Flush Water System, Cap and test for leaks.

And then we are done......